Abcourt Mines mills 5,581 tonnes of ore in October

2026-11-23 16:47 ET - News Release

Mr. Pascal Hamelin reports

ABCOURT MINES REPORTS OCTOBER MINING AND MILLING RESULTS AND ANNOUNCES SIGNING OF A THREE-YEAR COLLECTIVE AGREEMENT

Abcourt Mines Inc. has provided an update on its mining and milling operations at the Sleeping Giant mine for the month of October, along with the progress of work in November.

This update reflects a planned slowdown in October due to a scheduled maintenance shutdown at month-end, followed by a strong restart in early November that positions the operation for a full month of sustained production.

Highlights:

  • Mill throughput: A total of 5,581 tonnes of ore was milled in October, with mill operating availability of 89 per cent.
  • Head grade and recovery: The average mill head grade was 2.05 grams per tonne gold, while recovery reached 91.4 per cent.
  • Gold production and pours: The mill produced 336 ounces of gold during the period, and 246 ounces of gold were poured as dore bars.
  • Gold-in-circuit inventory: At the end of October, 832 ounces of gold remained in the mill circuit inventory.
  • Definition drilling and underground grades: Definition diamond drilling exceeded monthly targets with 4,108 metres drilled, while long-hole blasting returned an outstanding average grade of 5.00 g/t gold.
  • Sustained ramp-up in November (Zone 20): As of Nov. 19, 4,070 tonnes of ore had already been mined from Zone 20, exceeding total underground tonnage mined during the entire month of October (3,080 tonnes).
  • Educational partnership and next-generation work force (CFPBJ): The company hosted a cohort of 10 students from the Centre de formation professionnelle de la Baie-James (CFPBJ), leading to the hiring of six apprentice miners, with a new cohort of 12 students to be welcomed starting Nov. 25, 2026.
  • Stable labour relations: On Nov. 16, 2026, a new three-year collective agreement was signed, ratified by 100 per cent of employees.

Detailed sources and mining performance (October):

In October, operations were impacted by a planned maintenance shutdown at month-end aimed at ensuring the reliability of the facilities. Underground and milling activities were distributed as follows:

  1. Underground mining (3,080 tonnes at 1.99 g/t Au): sourced from development headings (1,812 tonnes) and long-hole stopes (1,268 tonnes);
  2. Underground development and hoisting: a total of 111 metres of development were completed, split between sublevels (85 m/286 m), track drifts (18 m/226 m) and vertical development (eight m/53 m); hoisting reached 3,334 tonnes of ore and 2,471 tonnes of waste;
  3. Diamond drilling and long-hole blasting: definition diamond drilling totalled 4,108 metres; in long-hole drilling and blasting, 1,039 metres were drilled and 812 tonnes were blasted at an average grade of 5.00 g/t Au;
  4. Mill processing: the mill processed 5,581 tonnes at an average grade of 2.05 g/t Au, representing 368 ounces, with a recovery rate of 91.4 per cent and operating availability of 89 per cent, yielding 336 ounces of gold produced and 246 ounces poured, bringing gold-in-circuit inventory to 832 ounces.

The comparative table below summarizes key operating performance indicators for September and October.

With full operations resuming in early November, the corporation is proud to report progress at its main stopes.

Human resources, labour relations and vocational training:

  • Signing of a new collective agreement: On Monday, Nov. 16, 2026, a new collective agreement was signed for employees of the Sleeping Giant mine, confirming its entry into force for a three-year term. The agreement is the outcome of six days of intensive collective bargaining conducted in a spirit of openness, respect and collaboration between the parties. The new labour contract was ratified by 100 per cent of employees, providing a stable and predictable labour relations framework for the next three years.
  • Vocational training and recruitment (CFPBJ): The current cohort of 10 students from the Centre de formation professionnelle de la Baie-James (CFPBJ), enrolled in the ore extraction program, will complete their training on Nov. 24. Originally hosted at another mine site, the cohort had to continue its program in a new setting after operations at that site were paused; Abcourt stepped in to ensure the continuity and full completion of their training. With recruitment in mind, two speed-interview sessions were held with the students, following which six of the 10 graduates will be hired as apprentice miners, helping to meet the corporation's current work force needs.
  • Welcoming a new cohort: Abcourt will also welcome a new cohort of 12 students from the CFPBJ starting Nov. 25, whose training program will run through March, 2027. This collaboration is a valuable opportunity to help train the next generation of miners while building a pool of trained candidates to meet future recruitment needs.

Pascal Hamelin, president and chief executive officer of Abcourt Mines, stated: "Although the planned maintenance shutdown at the end of October temporarily reduced our mining and milling volumes compared with September, this work was essential to ensure the long-term reliability of our facilities. The work was completed on schedule, and kudos to the teams who took part in the planned shutdown. In addition, the increase in our gold-in-circuit inventory to 832 ounces provides immediate leverage for our upcoming pours. The pace we have seen since restarting in November, with 4,070 tonnes already mined from Zone 20 in less than three weeks -- exceeding our underground tonnage for all of October -- confirms our ability to deliver a full month of sustained production. Furthermore, the unanimous 100-per-cent ratification of our three-year collective agreement and the hiring of six CFPBJ graduates reflect the exceptional engagement of our teams and strengthen our next-generation work force on the ground."

Qualified person

Pascal Hamelin, PEng, president and chief executive officer of the corporation, has reviewed and approved the technical information contained in this press release. Mr. Hamelin is a qualified person as defined by National Instrument 43-101.

About Abcourt Mines Inc.

Abcourt Mines is a Canadian gold development company with properties strategically located in northwestern Quebec, Canada. Abcourt owns the Sleeping Giant mine and mill and the Flordin property, where it focuses its activities.