Mr. William Willoughby reports
CENTURY LITHIUM RECEIVES NOTICE OF COMPLETION AND ACCEPTANCE OF BASELINE STUDIES FOR ANGEL ISLAND LITHIUM PROJECT, NEVADA USA
The U.S. Bureau of Land Management (BLM), Battle Mountain District, Tonopah Field Office, has determined that baseline data collection and reporting are complete for Century Lithium Corp.'s 100-per-cent-owned Angel Island lithium project in Esmeralda county, Nevada. The BLM has also determined that the appropriate National Environmental Policy Act (NEPA) review level for the project is an environmental impact statement (EIS).
"This is a significant step for Angel Island. Having the BLM accept and confirm our baseline studies as complete reflects years of dedicated effort by our team and puts the project on the path to a record of decision," said Bill Willoughby, president and chief executive officer of Century Lithium. "With the NEPA level of review now set, a clear federal process is established and we are well positioned to move Angel Island forward as a key source of domestic lithium for the U.S. battery supply chain."
Baseline completion and acceptance
In a letter dated Nov. 13, 2026, the BLM notified Century Lithium's wholly owned subsidiary, Cypress Holdings (Nevada) Ltd., that it had reviewed the baseline resource data submitted for the project. The BLM determined that baseline data collection is complete for all resources its interdisciplinary team identified as relevant to the proposed action, including the additional baseline studies completed for the proposed water supply pipeline route and well field. This follows the BLM's earlier determination that the mine plan of operations and Nevada reclamation permit application (PoO) for Angel Island is complete under 43 CFR paragraph 3809.411 (see news release dated Nov. 9, 2026).
NEPA determination
In the same letter, the BLM determined that an EIS is the appropriate level of NEPA analysis for the project. The EIS will be prepared in accordance with NEPA, the U.S. Department of the Interior's (DOI) NEPA procedures at 43 CFR Part 46 and the DOI NEPA Handbook. The BLM will serve as lead agency for the federal environmental review. The U.S. Environmental Protection Agency, the Nevada Department of Wildlife, Esmeralda County and Nye County have agreed to participate as co-operating agencies.
The proposed action under review includes an open-pit, two overburden stockpiles, two low-grade ore stockpiles, a dry-stack tailings storage facility, roads, ancillary facilities (warehouse and office, shop and laboratory), and a processing and leaching facility. The project is designed for a projected mill feed of 5.5 million tonnes per year (at 15,000 tonnes per day), with estimated average annual production of 27,400 tonnes per year of lithium carbonate.
Next steps toward environmental review
With baseline studies accepted and the level of NEPA review set, the third party NEPA contractor will continue preparation of the supplemental information report, which will support development of the supplemental environmental reports that form the basis of the EIS. Once the public scoping period and the NEPA analyses are complete, the PoO will be revised as needed for consistency, after which the BLM may issue a record of decision for the project.
Permitting timeline
Angel Island is a transparency project under the Federal Permitting Improvement Steering Council's FAST-41 program. The permitting dashboard for federal infrastructure projects currently shows a target date of Feb. 4, 2028, for issuance of the record of decision for the project. As with any federal schedule, this timetable is subject to change as the review progresses and the company will provide updates as key milestones are reached.
Qualified person
The scientific and technical information in this news release was reviewed and approved by Daniel W. Kalmbach, CPG, vice-president, exploration and resource development, of Century Lithium, who is a non-independent qualified person as defined by National Instrument 43-101, Standards of Disclosure for Mineral Projects.
All references to mining, processing and economics for Angel Island herein are from the updated National Instrument 43-101 technical report on the feasibility study of the Clayton Valley lithium project, Esmeralda county, Nevada (the project is now known as Angel Island), with an effective date of Jan. 3, 2026, which is available on SEDAR+ and the company's website.
About Century Lithium Corp.
Century Lithium is an advanced-stage lithium development company focused on its 100-per-cent-owned Angel Island lithium project in Esmeralda county, Nevada. Angel Island hosts one of the largest known sedimentary lithium deposits in the United States and is designed with an integrated, end-to-end process for the on-site production of battery-grade lithium carbonate to support the electric vehicle and battery storage markets.
The company has developed a patent-pending process that incorporates hydrochloric acid leaching combined with direct lithium extraction to produce battery-grade lithium carbonate. As part of the integrated chlor-alkali process, Angel Island is designed to produce sodium hydroxide as a co-product, with planned surplus sales expected to lower operating costs, reduce reliance on externally sourced reagents and minimize environmental impacts.
Century Lithium is currently advancing Angel Island through the permitting process.