Robex Resources begins commissioning at Kiniero

2025-11-17 09:49 ET - News Release

Mr. Matthew Wilcox reports

Commissioning commences as Kiniero tracks towards Q4 first gold

Robex Resources Inc. has provided a November, 2025, project construction update for its Kiniero gold project in Guinea, West Africa. Robex is on track to deliver first gold at Kiniero in Q4 CY (calendar year) 2025.

Highlights:

  • Commissioning and operations team fully mobilized to site at Kiniero gold project as Robex prepares for first gold in Q4 CY 2025;
  • First ore delivered to the ROM (run-of-mine) pad, with mining contractor fleet mobilization nearing completion;
  • Grade-control drilling completed over Sabali pit;
  • Tailing storage facility is nearing completion and will be ready for ore commissioning in the process plant;
  • Installation and testing of power station engines completed and ready for energization;
  • Electrical and precommissioning of process plant progressing in line with commissioning priority activities;
  • Precommissioning of HV (high-voltage) switchgear completed and ready for testing; energization planned for this week;
  • Communication network installed in process plant, connected to the plant control system and energized;
  • CIL (carbon-in-leach) motor control centre energized and function testing of drives commenced;
  • CIL train A tanks filled with water and ready for load testing the agitators and intertank screens;
  • SAG (semi-autogenous grinding) mill drive train installed and aligned and SAG mill inching drive energized; ball mill to follow.

Robex's managing director and chief executive officer, Matthew Wilcox, said: "Kiniero is moving closer to completion each month, and it is pleasing to see this progress continue in a safe and methodical manner, maintaining our schedule to achieve first gold in 2025. Commencement of process plant commissioning is now under way and is yet another major milestone in progressing towards first gold.

"Grade control drilling is completed, and ore has been delivered to the ROM pad in preparation for feeding the mill, while most other aspects of the project are nearing completion and remaining on schedule to achieve our targets.

"Robex is fully funded and is on budget for Kiniero's build completion."

Robex remains very well positioned to complete construction of Kiniero, which remains on schedule to realize first gold production in Q4 CY 2025.