GoGold keeps Los Ricos South on track for 2028 pour

2026-11-23 16:42 ET - News Release

Mr. Brad Langille reports

GOGOLD PROVIDES UPDATE ON LOS RICOS SOUTH CONSTRUCTION

GoGold Resources Inc. has provided an update on construction at its Los Ricos South project in Jalisco, Mexico. The project is progressing on schedule, and the company reiterates first silver pour in the second quarter of 2028.

"Construction at Los Ricos South continues to progress according to plan with site clearing and earthworks about halfway complete," said Brad Langille, president and chief executive officer. "Reflecting on recent volatility in the precious metals, it is good to note that our project is a very high-margin project, which is less impacted by a decrease in metal price than most. Our very strong balance sheet and substantial cash flows generated at our operating mine in Parral further derisks the project and we do not foresee any need for future equity or debt offerings to complete the project. Based on internal estimates using $45/oz silver, we see our cash reserves maintaining a minimum of $100-million (U.S.) over the course of the build."

Los Ricos South construction highlights

  • Active site works -- site clearing and earthworks at the process plant site are approximately 48 per cent complete with 180 contractor personnel on site;
  • All long-lead orders placed -- all long-lead equipment orders have been placed, with procurement continuing on schedule. The long-lead orders include the SAG mill, tailings filter, crusher, electrical switchgear, Merrill-Crowe plant, conveyors, slurry pumps, hydrocyclones, feeders and screens, and paste plant pumps;
  • Plant design -- the design by M3 and DENM Engineering is 95 per cent complete. Vendor design specifications being inputted to the finals design;
  • Paste plant design -- the design is being carried out by RMS of Sudbury, Canada. The current progress will allow the start of construction in January, 2027;
  • Underground mining contractor selected -- Cominvi planned to mobilize to site in Q4 2026. Portal designs have been completed by WSP and associated earthworks have begun;
  • Schedule maintained -- construction and procurement remain on or ahead of plan, with first silver pour reiterated for Q2 2028.

To date, the company has spent $21-million (U.S.) on the project, with $52-million (U.S.) committed to date. Following are the key schedule milestones:

Los Ricos South key schedule milestones

  • Earthworks commenced -- August, 2026;
  • Underground mine plan optimization commenced -- August, 2026;
  • Start of powerline installation -- Q1 2027;
  • Concrete foundation pouring -- January, 2027;
  • Portal development/ramp blasting -- January, 2027;
  • Paste plant construction begins -- January, 2027;
  • Hill-slope stabilization/mining -- Main/Abra zone -- March, 2027;
  • SAG mill delivery to site -- May, 2027;
  • Plant commissioning begins -- January, 2028.

Technical information contained in this news release with respect to GoGold has been reviewed and approved by Mr. Bob Harris, PEng, who is a non-independent qualified person for the purposes of NI 43-101.

About GoGold Resources Inc.

GoGold Resources (Toronto Stock Exchange: GGD) is a Canadian-based silver and gold producer focused on operating, developing, exploring and acquiring high-quality projects in Mexico. The company operates the Parral tailings mine in the state of Chihuahua and has the Los Ricos South project, which is in development with a construction decision approved by the board, and Los Ricos North exploration and development project, both in the state of Jalisco. Headquartered in Halifax, N.S., GoGold is building a portfolio of low-cost, high-margin projects.

We seek Safe Harbor.

© 2026 Canjex Publishing Ltd. All rights reserved.