ORIGINAL: Magna Mining Reports Results of Crean Hill Pre-Feasibility Study With Construction to Begin in 2027

2026-10-21 06:45 ET - News Release

SUDBURY, Ontario, Oct. 21, 2026 (GLOBE NEWSWIRE) -- Magna Mining Inc. (TSX: NICU) (OTCQX: MGMNF) (FSE: 8YD) (“Magna” or the “Company”) is pleased to announce the results of a Pre-Feasibility Study (“PFS”) prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) for the 100% owned Crean Hill Project (“Crean Hill”), located in the South Range of the Sudbury Basin, northeastern Ontario. All amounts are expressed in Canadian dollars unless otherwise indicated.

Crean Hill PFS Highlights:

  • Twelve-year commercial mine life with over 11 million tons of probable reserves: The Crean Hill PFS contemplates underground mining of 11.4 million tons of probable reserves at an average mining rate of approximately 2,400 tons per day during the twelve-year commercial mine life.
  • Robust production profile with significant precious metals byproduct credits: Average annual payable copper equivalent (“CuEq”)1,2 production of 35.5 million pounds (“lbs”) during commercial production at all-in sustaining costs (“AISC”) of US$3.55 per CuEq payable lb, including 42 thousand ounces of precious metals (platinum + palladium + gold) on average per year which contribute approximately 38.9% of revenues during this time.
  • Attractive base case economics with strong commodity price leverage: Assuming base case commodity prices1, the Crean Hill PFS estimates payback in 1.5 years with an after-tax Internal Rate of Return (“IRR”) of 43.4% and an after-tax NPV7% of $251.0 million. Pre-tax cash flows average approximately $65.2 million per year and increase to $96.2 million per year using September 2026 average commodity prices1, while the after-tax NPV7% increases to $406.1 million, the IRR improves to 65.4%, and the payback period falls to 0.8 years.
  • Manageable initial capital spread over a three-year pre-commercial production period: Initial capital costs from January 1, 2027 are estimated to be $127.0 million. This initial capital is expected to be offset by refundable tax credits3 of $17.2 million and pre-commercial production operating cash flow of approximately $37.4 million using base case price assumptions, leaving a calculated net initial funding requirement of $72.4 million. Construction spending is expected to ramp up gradually over a three-year period with first ore sales in late 2027 and commercial production achieved in early 2030.
  • Positive potential impact from the recently announcedProductivity Mega Deduction: Incorporation of the Productivity Mega Deduction (“PMD”)4 could reduce the estimated federal taxes payable over the life of mine, especially during the early years of commercial production. By accelerating the utilization of certain tax deductions via the PMD, the Crean Hill PFS after-tax NPV7% would improve by $5.7 million to $256.7 million and the IRR would increase to 45.5%.

Crean Hill construction to commence in 2027: Based on the results of the PFS (summarized in Table 1), the Company’s Board of Directors has approved construction of the Crean Hill project, which will commence in 2027. In the interim, the Company will continue with detailed engineering work, surface site preparations including installation of grid power and recruitment of additional personnel.

Crean Hill exploration drilling now underway: In addition, an exploration diamond drill rig has been mobilized to the Crean Hill Project and has started drill testing new targets for additional footwall copper and precious metals-rich mineralization.  

1 Base case price assumptions: US$5.10/lb Cu, US$8.00/lb Ni, US$20.00/lb Co, US$3,600/oz Au, US$1,500/oz Pt, US$1,200/oz Pd, US$45.00/oz Ag; CAD/USD $1.385. Illustrative spot price case assumptions based on September 2026 average prices: US$6.55/lb Cu, US$7.50/lb Ni, US$24.90/lb Co, US$4,320/oz Au, US$1,785/oz Pt, US$1,310/oz Pd, US$64.50/oz Ag; CAD/USD $1.370.
2 Payable CuEq production considers base case price assumptions and modeled recovery and payabilities for each metal.
3 Assumes $17.2 million in refundable tax credits via the Clean Technology Manufacturing Investment Tax Credit (CTM-ITC).
4 On September 15, 2026, the Canadian federal government announced the Productivity Mega Deduction (“PMD”), allowing businesses to immediately deduct the cost of a broad range of capital assets, rather than claiming those deductions over time. The PMD is subject to legislative approval.  

Jason Jessup, CEO of Magna Mining, stated, “We are pleased to announce the results of the Crean Hill PFS, which demonstrates robust economics and a clear path toward construction. The base case delivers an after-tax IRR of 43.4% and a 1.5-year payback period. Crean Hill also benefits from a balanced mix of copper, nickel and precious metals production, providing meaningful exposure to seven payable metals without an overreliance on any single commodity.

The PFS outlines a 12-year commercial mine life and C$72.4 million of net initial funding after refundable tax credits and pre-commercial production operating cash flow. The development plan builds on the core approach established in the 2024 Crean Hill PEA—advancing a new ramp from surface before re-establishing shaft hoisting—and leverages the project’s brownfield setting and existing infrastructure. On the strength of these results, our Board has approved moving forward with construction in 2027. In the interim, our team will continue detailed engineering and design, advance procurement of long-lead items, site preparation and recruitment of the additional people needed to execute the plan. We are also excited to have initiated exploration drilling at Crean Hill for the first time since 2024. I would like to thank everyone whose work and commitment have advanced the project to this important milestone.”

 
Table 1: Key Crean Hill PFS Project Metrics
 
Production Profile Unit
Commercial Mine Life12.0years
Mining rate12,397tons per day
Total mined ore (Probable Reserve)11,358,861tons
CuEq head grade1,52.99% 
Avg. annual copper production19.5million payable lbs
Avg. annual nickel production17.5million payable lbs
Avg. annual precious metals production142.0koz Pt+Pd+Au payable
Avg. annual CuEq production1,535.5million payable lbs
Operating Costs Unit
Production costs LOM$152.62C$ per ton processed
Total cash costs LOMUS$3.10US$ per CuEq payable lb
All-in sustaining costs LOMUS$3.55US$ per CuEq payable lb
Capital Costs  
Initial capital2$127.0
C$ million
Refundable tax credits-$17.2
C$ million
Pre-commercial production operating cash flow-$37.4
C$ million
Net initial funding$72.4
C$ million
LOM sustaining capital$261.7
C$ million
Project EconomicsBase Case3Spot Price Case4
Avg. annual operating cash flow1 (C$ million)C$87.3 MC$118.3 M
Pre-tax NPV7% (C$ million)C$329.7 MC$554.3 M
After-tax NPV7% (C$ million)C$251.0 MC$406.1 M
After-tax IRR43.4%
65.4%
After-tax cash flow LOM (C$ million)C$507.8 MC$779.2 M
After-tax payback period1.5 years0.8 years
After-tax NPV7% with PMD6 (C$ million)C$256.7 MC$412.4 M
After-tax IRR with PMD645.5%
68.0%


1
Production averages cover commercial production from Years 4-15. CuEq head grade is on a contained basis covering Life of Mine, CuEq determined using base case metal price assumptions. Tons are short tons (2,000 lb).
2Year 1-3 pre-commercial production capital, after equipment financing timing effect; before operating cash flow and refundable tax credits. Payback is measured from end of Year 3.
3US$5.10/lb Cu, US$8.00/lb Ni, US$20.00/lb Co, US$3,600/oz Au, US$1,500/oz Pt, US$1,200/oz Pd, US$45.00/oz Ag; CAD/USD $1.385.
4Illustrative spot-price case based on September 2026 average prices: US$6.55/lb Cu, US$7.50/lb Ni, US$24.90/lb Co, US$4,320/oz Au, US$1,785/oz Pt, US$1,310/oz Pd, US$64.50/oz Ag; CAD/USD $1.370.
5See Tables included with Figures 2 and 3 for grades and contribution of specific metals.
6On September 15, 2026, the Canadian federal government announced the proposed Productivity Mega Deduction (“PMD”), which would permit the immediate deduction of certain eligible capital expenditures for income tax purposes. As the PMD has not yet been enacted into law, the benefit has been excluded from the base-case economic analysis and is presented separately as a sensitivity.


Figure 1: Location of Crean Hill and Key Sudbury Infrastructure

Figure 1

PFS Overview

The Crean Hill project, located in the South Range of the Sudbury Basin (Figure 1), is a brownfield redevelopment of the past-producing nickel-copper-precious metals (platinum, palladium, gold, silver) Crean Hill Mine. Since 1906, the Crean Hill mine site underwent multiple phases of open-pit and underground mining with the most recent operations having ceased in 2002. During this period, approximately 20.4 million tonnes of ore were produced at an average grade of 1.31% nickel, 1.09% copper, and 1.56 g/t total precious metals (platinum + palladium + gold). The underground workings have subsequently flooded, and all surface infrastructure dismantled. In November 2022, the Company acquired Lonmin Canada Inc., including the past-producing Crean Hill Mine. The Company holds the mining rights from the top of the existing concrete capped Shaft #2 (former historic Crean Hill Mine production shaft) to a depth of 4,500 feet (1,372 metres). Vale Canada Limited (Vale) continues to hold all Mining Rights below 4,500 feet. Topics covered in the PFS include the mining design basis, geotechnical design basis, hydrogeology and dewatering, mine access and design, mining method and stope design, development, production schedule, metallurgy, mobile fleet, workforce, ventilation, backfill, material handling and grade control. The PFS was prepared by SGS Geological Services (SGS) with the assistance of Magna’s Projects team, as well as insights from current operations at the Company’s McCreedy West Mine in Sudbury. The PFS incorporates geological information collected by the Company including 199 diamond drill holes for a total of 44,895 metres of drilling between November 2022 and December 2024, the results from the 20,000 tonne bulk sample program executed in the second half of 2024, as well as historic information from the previous underground mining operations at Crean Hill.

Mine Plan and Production Schedule

The Crean Hill PFS mine plan (summarized in Table 1) envisions an underground mining operation, with the probable reserves being hauled and sold to an existing third-party mill in Sudbury. Initial mining is contemplated by ramp access via a new surface portal with the eventual rehabilitation and re-establishment of the historic Shaft #2 for ore hoisting as mining progresses deeper. The PFS assumes go-forward capital spending begins on January 1, 2027 and ramps up over the first three years with initial ore generated towards the end of Year 1 and commercial production anticipated at the end of Year 3 (Figure 2). At the target commercial production rate of approximately 2,400 short tons per day, the mine plan includes 11.4 million short tons over a 12.0 year mine life.

The mineralized zones incorporated in the PFS mine plan include both contact ore (including the Main, Intermediate, 99 and 9400 Zones) as well as footwall ore (the 109 FW Zone). The 11.4 million short tons of probable reserves are derived from the current Crean Hill Mineral Resource Estimate.

Figure 2 shows annual mill feed by ore type and contained CuEq head grade. During commercial production (Years 4-15), ore shipped and processed averages 875,000 tons per year. The contained CuEq head grade uses base case metal prices, without recovery, payability, or cost deductions and averages 2.99% CuEq over the twelve-year commercial mine life. Figure 3 shows payable metal production expressed as CuEq, using the modeled recoveries and payabilities. Precious metal head grades in Figure 2 are in grams per tonne. Annual payable metal production during the twelve-year commercial mine life averages 35.5 million lbs CuEq, comprised of 9.5 million lbs copper, 7.5 million lbs nickel, 6,400 oz gold, 15,600 oz platinum, and 19,900 oz palladium.  


Figure 2: Crean Hill PFS Production Schedule & Contained Copper Equivalent Grade

Figure 2

Year Y 1Y 2Y 3Y 4Y 5Y 6Y 7Y 8Y 9Y 10Y 11Y 12Y 13Y 14Y 15
Ore shipped
(short tons)
 8,139401,572450,372887,305887,056887,533888,744887,497887,557888,088887,387832,259887,188888,906789,259
Contained
Grades
CuEq (%)2.053.122.963.043.343.782.872.562.922.822.763.132.813.182.67
Cu
(%)
0.490.770.710.680.560.530.600.570.690.690.680.680.510.570.57
Ni
(%)
0.591.010.800.700.590.520.680.680.790.810.760.560.570.580.56
Co
(%)
0.020.030.030.020.020.020.020.020.030.030.030.020.020.020.02
Au
(gpt)
0.210.250.330.390.610.680.320.220.270.240.220.590.470.660.31
Pt
(gpt)
0.430.570.740.871.311.930.960.730.660.620.651.001.091.200.92
Pd
(gpt)
0.390.350.611.091.692.301.040.800.940.680.781.301.091.171.16
Ag
(gpt)
0.960.871.310.741.072.840.830.570.991.051.230.580.551.460.97
                 

Figure 3: Crean Hill PFS Copper Equivalent Payable Metal Production

Figure 3

Year Y 1Y 2Y 3Y 4Y 5Y 6Y 7Y 8Y 9Y 10Y 11Y 12Y 13Y 14Y 15
Payable
Metal
CuEq
(million lb)
0.2117.3318.0936.9240.9046.6034.3529.8835.1633.7732.8435.7633.4638.5327.96
Cu
(million lb)
0.075.515.6910.788.938.379.579.0510.9710.8510.7310.108.119.078.06
Ni
(million lb)
0.065.925.068.426.625.638.048.139.7010.109.265.846.386.605.61
Co
(million lb)
0.0010.0600.0510.0840.0680.0580.0880.0880.0920.1020.0920.0600.0640.0670.064
Au
(koz)
0.0241.4582.4726.10210.36611.8444.6422.6543.5372.9422.6809.4367.62611.3763.982
Pt
(koz)
0.0413.1095.15613.51122.55334.92915.25110.1158.6367.8538.59615.12417.98320.28212.937
Pd
(koz)
0.0381.5004.22318.34331.35243.77417.25612.27415.1459.74611.89721.89218.76720.65918.034
Ag
(koz)
-----27.941---------
                 

Capital and Operating Costs

The Crean Hill Project is a former operating mine site with existing infrastructure such as year-round access, nearby electrical power line grid, and available water sources. Pre-existing infrastructure as well as capital invested prior to the end of 2026 is treated as sunk capital for the purposes of the PFS.

Estimated initial capital is $127.0 million, including $17.9 million of contingency. The estimate comprises capital expenditure from January 1, 2027 to the start of commercial production at the end of Year 3, reflecting the timing of equipment financing (Table 2). Estimated initial capital is presented after equipment financing timing effects. Deferred equipment purchase payments are included in subsequent years. Initial capital is estimated to be $33.0 million in Year 1, $35.0 million in Year 2, and $59.0 million in Year 3. The after-tax cash flow model incorporates the Clean Technology Manufacturing investment tax credits. Eligibility and receipt of those credits remain subject to the applicable requirements and the Company's tax review. While pre-commercial production operating cash flow and the benefit of refundable tax credits does not reduce the initial capital required, it does help to decrease the net cash outlay at the end of the ramp-up period to an estimated $72.4 million.

Estimated sustaining capital from commercial production at the end of Year 3 onward is $261.7 million.

 
Table 2: Crean Hill Initial Capital Costs
 
Initial CapexC$ million
Mining Capital 
Underground development$35.0
Mobile fleet (after financing timing effects)$38.9
Underground infrastructure$8.7
Subtotal$82.6
Surface Infrastructure Capital 
Ventilation$2.9
Water management$3.3
Power distribution & substation$2.9
Backfill plant & reticulation$4.4
Other surface facilities$1.9
Subtotal$26.4
Contingency$17.9
Total initial capital (Year 1-3)1$127.0
Refundable tax credits-$17.2
Pre-commercial production operating cash flow-$37.4
Net initial funding$72.4


1
Figures may not sum exactly due to rounding

The Company’s producing McCreedy West Mine is also located in Sudbury and provides an operating cost and productivity benchmark. Average life-of-mine operating costs in the Crean Hill PFS are $152.62 per short ton processed (Table 3). Cash costs are US$3.10/lb payable CuEq and AISC are US$3.55/lb payable CuEq. Cash costs and AISC use the commercial production periods and AISC includes estimated sustaining capital. These are non-GAAP measures and may not be comparable with similarly named measures used by other companies.

 
Table 3: Crean Hill PFS Operating Costs
 
Operating CostsLOMUnit
Mining costs$77.47
C$/ton shipped
Surface & processing costs$57.04
C$/ton shipped
General & site administration costs$18.11
C$/ton shipped
Total Operating Costs$152.62
C$/ton shipped
Total Cash CostsUS$3.10US$/lb CuEq payable
AISCUS$3.55US$/lb CuEq payable


Project Economics & Sensitivity

At the base-case prices in Table 4, recovered payable metal value comprises the following revenue share 27.3% copper, 34.4% nickel, 12.4% gold, 12.5% platinum, 12.5% palladium, 0.9% cobalt, 0.1% silver. The average annual revenue during commercial production is $223.4 million while pre-tax cash flows average approximately $65.2 million per year (Figure 4). The Crean Hill PFS base case pre-tax NPV7% is $329.7 million and the after-tax NPV7% is $251.0 million, with an after-tax IRR of 43.4% and payback of 1.5 years. The after-tax NPV7% incorporates the Company’s current tax assumptions, including an estimated benefit of $40.0 million LOM from the Clean Technology Manufacturing investment tax credit. The realization of this tax benefit remains subject to the Company’s ability to satisfy the applicable legislative and tax filing requirements.

An illustrative spot-price case scenario based on average metal prices during September 2026 returns a pre-tax NPV7% of $554.3 million, an after-tax NPV7% of $406.1 million, an after-tax IRR of 65.4% and payback of 0.8 years. The average annual revenue during commercial production in the spot-price case scenario is $255.1 million while pre-tax cash flows would average approximately $96.2 million per year. Tables 4 and 5 and Figure 5 show fixed mine plan sensitivities. Price-only sensitivities hold the base exchange rate constant; the illustrative spot case applies USD/CAD 0.730 to revenue and U.S. dollar milling charges, with other cost translations held at the base case rate.

The base case after-tax economic results exclude any benefit associated with the PMD tax incentive. For illustrative purposes, a separate tax sensitivity was completed assuming the Company is eligible to claim available PMD deductions on qualifying expenditures. Under this scenario, the base case after-tax NPV7% increases to $256.7 million and the after-tax IRR increases to 45.5%. This legislation remains subject to approval.

Figure 4: Crean Hill PFS Pre-Tax Cash Flow

Figure 4

 
Table 4: Crean Hill PFS Economic Summary & Sensitivity Analysis
 
Price DeckUnit-10%
Base Case+10%Spot Price Case
CopperUS$/lb$4.59
$5.10$5.61$6.65
NickelUS$/lb$7.20
$8.00$8.80$7.55
GoldUS$/oz$3,240
$3,600$3,960$4,400
PlatinumUS$/oz$1,350
$1,500$1,650$1,850
PalladiumUS$/oz$1,080
$1,200$1,320$1,350
SilverUS$/oz$40.50
$45.00$49.50$65.00
CobaltUS$/lb$18.00
$20.00$22.00$22.00
USD/CADx0.722
0.7220.7220.730
LOM Economics     
Revenue LOMC$ million$2,572.3
$2,896.6$3,220.8$3,300.7
Operating cash flow LOMC$ million$765.0
$1,079.5$1,394.0$1,475.6
Pre-tax cash flow LOMC$ million$362.5
$677.0$991.5$1,073.1
After-tax cash flow LOMC$ million$291.7
$507.8$723.4$779.2
Annual Averages (Commercial Production)       
RevenueC$ million per year$198.5
$223.4$248.4$255.1
Operating cash flowC$ million per year$63.1
$87.3$111.5$118.3
Pre-tax cash flowC$ million per year$41.0
$65.2$89.4$96.2
After-tax cash flowC$ million per year$33.1
$49.1$65.0$69.7
Net Present Value & IRR     
Pre-tax NPV7%C$ million$149.9
$329.7$509.6$554.3
After-tax NPV7%C$ million$125.6
$251.0$375.6$406.1
Pre-tax IRR%23.5%
42.7%62.4%65.5%
After-tax IRR%25.1%
43.4%62.8%65.4%
Paybackyears2.3
1.5 0.80.8
After-tax NPV7% / initial capexx1.0x2.0x3.0x3.2x
After-tax NPV7% with PMDC$ million$130.6
$256.7$381.8$412.4
After-tax IRR with PMD%26.6%
45.5%65.5%68.0%



Table 5: Base Case After-tax NPV7% Sensitivity Analysis (C$ million)
 
Change-20%
-10%
0%
10%
20%
Copper$183.9$217.4$251.0$284.5$317.9
Nickel$162.8$206.9$251.0$294.9$338.7
Metal prices-$3.7
$125.6$251.0$375.6$499.2
Operating costs$389.3$320.4$251.0$181.3$111.2
Capital costs$306.5$278.7$251.0$223.2$195.4


Figure 5: Sensitivity Analysis

Figure 5

Mining, Processing and Infrastructure

As illustrated in Figure 6, the PFS adopts an underground bulk longhole mining method with access to both transverse and longitudinal stopes via ramps and drifts suitable for medium-to-large-size diesel-powered mobile equipment. Sublevel spacing varies between 80 and 115 feet vertically. Access to the underground workings will be established in a phased approach. Initially, a box cut and portal will be constructed and an access ramp developed to support initial production from the upper portion of the mine. Ore will be generated prior to commercial production from areas above the 500 Level and will rely mostly on repair and rehabilitation of existing ventilation and service raises. Mining above the 2000 Level will rely exclusively on a fleet of 50-ton haul trucks bringing ore, and waste as necessary, to surface up the ramp. As mining progresses deeper, reliance on newly excavated ventilation and egress raises along with the eventual reconstruction of a surface hoisting plant and shaft repair will allow ore to be hoisted from the 2000 Level shaft loading pocket. This will reduce the need for a larger haul truck fleet and the associated mine ventilation upgrade over the life of mine.

Longhole drilling will use self-propelled electric-hydraulic machines, and production blasting will be done with almost exclusively emulsion-type explosives. Mined-out stopes will be backfilled with a combination of unconsolidated rock fill, cemented sand fill and hydraulic fill depending on mining sequence and the availability of suitable waste rock over the course of mine life.  

In addition to basic surface infrastructure that will include shop, office and warehousing facilities, a sandfill plant, crushing and sampling tower and eventually a hoist & muck transfer system will be constructed, as well as conventional mine air ventilation and heating infrastructure.

Provision within the life of mine plan has been made for upgrades to the water treatment system associated with discharge to the environment from site. First by the installation of clarifiers to replace the existing pilot plant solids capture system, and eventually a more complex system to manage more complex chemicals.

Once on surface, ore will be reduced to a topsize of 1.5 inches via a contractor-operated surface crusher comprised of a combination of a jaw crusher (until hoisting begins) and cone crusher and then subsampled via the onsite sampling tower with representative subsamples dispatched to the sample preparation and analytical laboratory. Production lots of approximately 2,000 to 4,000 tons of ore will then be shipped to third party milling facilities located in Sudbury, Ontario.


Figure 6: Crean Hill Infrastructure and Geological Zones

Figure 6


Mineral Resources and Mineral Reserves

The Crean Hill Mineral Resource Estimate is presented below in Table 6 and is based on a 1.75% CuEq cutoff grade. The current Mineral Resources have been updated from the November 1, 2024 Mineral Resources stated in the Preliminary Economic Assessment, and have an effective date of April 15, 2026, which is the close out date for the final mine out models (as-builts) used to deplete historical mining. The underlying resource model parameters and drillhole database remains unchanged from the 2024 model, however the cutoff grade has been updated to 1.75% CuEq, based on the metal prices stated below and the model has been depleted with a more detailed mine-out model, to more accurately account for historical mining. Mineral Resources are inclusive of those resources which have been converted to Mineral Reserves. Allan Armitage, Ph.D., P. Geo. of SGS Geological Services is an independent Qualified Person as defined by NI 43-101 and is responsible for the current Crean Hill Mineral Resource Estimate.

 Table 6: Crean Hill Mineral Resource Estimate
 
               
 Deposit
Type
Cut-off Grade
CuEq%
Short
Tons
Metric
Tonnes
Cu %Ni %Co %Pt
(g/tonne)
Pd
(g/tonne)
Au
(g/tonne)
Ag
(g/tonne)
CuEq %NiEq % 
 Indicated 
 Contact1.75% CuEq17,820,00016,171,0000.881.000.030.931.090.361.022.961.88 
 Footwall1.75% CuEq604,000548,0000.740.410.013.182.591.384.253.622.31 
 Total Indicated1.75% CuEq18,424,00016,719,0000.870.990.031.001.140.401.122.981.90 
 Inferred 
 Contact Inferred1.75% CuEq884,000802,0000.590.700.031.031.740.330.292.331.48 
               

Crean Hill Mineral Resource Estimate Notes:

  1. The effective date of the Crean Hill Property Mineral Resource Estimate (MRE) is April 15, 2026. This is the close out date mine out models (as-builts).
  2. Allan Armitage, Ph.D., P. Geo. of SGS Geological Services is an independent Qualified Person as defined by NI 43-101 101 and is responsible for the current Crean Hill MRE. Armitage conducted multiple site visits to the Crean Hill Property including on May 25-26, 2022, July 25, 2023, July 02, 2024, July 25, 2024 and November 14, 2025.                          
  3. The classification of the current MRE into Indicated and Inferred mineral resources is consistent with current 2014 CIM Definition Standards - For Mineral Resources and Mineral Reserves.                                                 
  4. All figures are rounded to reflect the relative accuracy of the estimate and numbers may not add due to rounding. 
  5. The Crean Hill Mineral Resources are inclusive of those Mineral Resources which have been converted to Mineral Reserves.        
  6. The mineral resource is presented undiluted and in situ, constrained by 3D grade control resource models, and are considered to have reasonable prospects for eventual economic extraction. The mineral resource is exclusive of mined out material. 
  7. Mineral resources which are not mineral reserves do not have demonstrated economic viability. An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that most Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration. 
  8. The Crean Hill mineral resource estimate is based on a validated drill hole database which includes data from 3,892 surface and underground diamond drill holes completed between 1951 and March 2024 and totals 475,773 metres. The resource database totals 98,757 assay intervals, representing 197,536 metres of data.                         
  9. The mineral resource estimate is based on a three-dimensional (“3D”) resource model of the main mineralization and a broader dilution envelope. 3D models of mined out areas were used to exclude mined out material from the current MRE. 
  10. Grades for Ni, Cu, Co, Pt, Pd, Ag and Au are estimated for each mineralization domain using ~2.0 m capped composites assigned to that domain. To generate grade within the blocks, the inverse distance squared (ID2) interpolation method was used for all domains.                                                                                  
  11. Specific gravity values were assigned to each block based on a regression formula defined by a database of 32,592 samples. SG=(0.2057xNi%+2.88).                                                                         
  12. Based on the size, shape, and orientation of the Crean Hill Deposit, it is envisioned that the deposits may be mined using both bulk and selective mining methods including Longhole Stoping and Mechanized Cut and Fill (MCAF) (mining methods that have long been utilized in the Sudbury region). The MRE is reported at a base case cut-off grade of 1.75% CuEq. The mineral resource grade blocks are quantified above the base case cut-off grade and within the constraining mineralized wireframes (considered mineable shapes).                                                 
  13. The underground base case cut-off grade of 1.75% CuEq considers metal prices of $7.30/lb Ni, $4.65/lb Cu, $14.85/lb Co, $1,225/oz Pt, $1,135/oz Pd and $3100/oz Au, metal recoveries of 85% for Ni, 91% for Cu,68% for Co,64% for Pt, 69.5% for Pd and70.5% for Au.                                                                         
  14. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. 
   
 Table 7: Crean Hill Mineral Reserve Estimate
 
            
 Deposit
Type
Short
Tons
Metric
Tonnes
Cu %Ni %Co %Pt
(g/tonne)
Pd
(g/tonne)
Au
(g/tonne)
Ag
(g/tonne)
 
 Probable 
 Contact10,935,0009,920,0650.620.680.020.921.080.381.00 
 Footwall423,861384,5200.550.310.012.352.151.043.20 
 Total Probable11,358,86110,304,5850.620.670.020.971.120.401.08 
            

Crean Hill Mineral Reserve Estimate Notes:

  1. The effective date of the Crean Hill Mineral Reserve estimate is September 30, 2026.
  1. Mineral Reserves are included within the estimated Mineral Resources.
  2. The Mineral Reserve estimate was prepared under the supervision of Mr. Henri Gouin, P.Eng., of SGS Geological Services and Mr. William van Breugel, P.Eng., Associate Engineer of SGS Geological Services, both considered Qualified Persons as defined by NI 43-101.
  3. Mineral Reserves are based on metal prices of US$4.65/lb Cu, US$7.30/lb Ni, US$14.85/lb Co, US$1225/oz Pt, US$1135/oz Pd, US$3100/oz Au, US$39/oz Ag. Metal recoveries considered are 91% for Cu, 85% for Ni, 68% for Co, 64% for Pt, 69.5% for Pd, 70.5% for Au and 70.5% for Ag.
  4. The estimate of Mineral Reserves may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The Mineral Reserve Estimate is not a guarantee of economic viability.
  5. A mine design cut-off grade of 1.5% NiEq in-situ was applied to each stope which, after considering recovery and payability, exceeds the estimated costs of sustaining development, equipment and fixed plant capital costs, and operating costs. An incremental stope optimization was subsequently completed using a cut-off grade of 1.2% NiEq.
  6. Stope tons and grades include dilution consisting of 20% and mining losses of 8%.
  7. Figures may not sum exactly due to rounding.                                                        

Construction Decision

Based on the results of the PFS prepared in accordance with NI 43-101 Standards of Disclosure for Mineral Projects, authored by independent and experienced Qualified Persons, the Company’s Board of Directors has approved the construction of the Crean Hill Mine. Preliminary work will commence immediately with surface site preparation, detailed engineering, procurement of long lead time items and recruitment of required personnel. The formal start of construction is expected in the first half of 2027.

An exploration diamond drill rig has been mobilized to the Crean Hill Project and has started drill testing new targets for additional footwall copper and precious metals-rich mineralization. Additional assay results will be released in due course.

Third Quarter Results

Magna will release financial and operating results for the third quarter of 2026 after market close on Wednesday November 11, 2026. In addition, the Company will hold a conference call and webcast to discuss these results on Thursday November 12, 2026 at 8:00am ET. 

To register for the conference call, please use the following link to obtain a Dial-in Number and PIN: https://register-conf.media-server.com/register/BI977e3342f4ac4bc7af8ea4829f6d91a0

To attend the webcast in listen-only mode, please use the following link: https://edge.media-server.com/mmc/p/6yc2zx2c

Technical Report Filing

The technical report in support of the above noted PFS will be filed by Magna Mining within 45 days of this news release.

Qualified Persons

The following Qualified Persons (QPs) oversaw the completion of the work in preparation of the PFS and are responsible for the contents:

Independent QP for Geology and Mineral Resource Estimates
Mr. Allan Armitage, Ph.D., P.Geo., of SGS Geological Services.
Mr. Armitage conducted a personal inspection of the site on May 25-26, 2022, July 25, 2023, July 02, 2024, July 25, 2024, and November 14, 2025.

Independent QP for Underground Mining and Financial Analysis
Mr. Henri Gouin, P.Eng., of SGS Geological Services.
Mr. Gouin conducted a personal inspection of the site on May 13, 2024 and November 14, 2025.

Independent QP for Underground Mining, Financial Analysis, Permitting and Environmental
Mr. William van Breugel, P.Eng., Associate Engineer of SGS Geological Services.

Independent QP for Processing and Recovery
Mr. David Middleditch, B.Eng., MIMMM, President and Principal Metallurgist of Libertas Metallurgy Limited.

The scientific and technical information in this press release has been reviewed and approved by David King, M.Sc., P.Geo., and Jeff Dawson, P.Eng. Mr. King is the Senior Vice President, Exploration and Geoscience for Magna Mining Inc. and is a qualified person under National Instrument 43-101. Mr. Dawson is the Director, Technical Services for Magna Mining Inc. and is a qualified person under National Instrument 43-101.

Cautionary Statement on Forward-Looking Statements

All statements, other than statements of historical fact, contained or incorporated by reference in this press release constitute “forward-looking statements” and “forward-looking information” (collectively, “forward-looking statements”) within the meaning of applicable securities laws. Generally, these forward-looking statements can be identified by the use of forward-looking terminology, such as “may”, “might”, “potential”, “expect”, “anticipate”, “estimate”, “believe”, “could”, “should”, “would”, “will”, “continue”, “intend”, “plan”, “target”, “forecast”, “prospective”, “significant”, “robust”, “rapid” or other similar words or phrases or variations thereof. Forward-looking statements are necessarily based upon a number of assumptions that, while considered reasonable by management at the time forward-looking statements are made, are inherently subject to business, market, economic, technical and other risks, uncertainties and contingencies that may cause actual results, performance or achievements to be materially different from those expressed or implied by forward-looking statements, including risks and uncertainties relating to the failure of additional drilling and assays to support assumptions, expectations or estimates of potential mineralization, metal tonnes or grade, the failure of additional drilling to support additional expansion or delineation of estimated resources or reserves, the failure to have accurately estimated declared mineral resources or mineral reserves, the failure of additional drilling to support production planning or replenish production, the failure to maintain an adequate rate of development or access to stopes to maintain production, the failure to realize expected or anticipated production rates, mine life, operating and capital costs, recoveries, processing methods, economic returns, cash flows, net present value, internal rate of return, payback period, government funding or tax incentives, commodity prices, exchange rates, future production, development and operating plans or expansions, permitting and project schedules or timelines, changes in project design, scope or development plans, delays in or the failure to obtain required permits, approvals or authorizations, environmental and regulatory risks, infrastructure and power supply risks, labour, equipment and supply-chain constraints, operational, geotechnical, metallurgical, engineering and construction risks, adverse weather, the lack of availability of drill rigs to implement exploration or other programs or the failure to proceed as quickly as planned with additional exploration, development, production or other drilling, continued delays for assay results, the failure to bring the Crean Hill mine back into commercial production subsequent to the completion of the PFS because of funding or technical issues, and other risks disclosed in the Company’s most recent annual information form for the year ended December 31, 2025, available on the SEDAR+ website (at: www.sedarplus.ca). The PFS is based on a number of assumptions and estimates that are subject to significant uncertainties and contingencies. There is no assurance that the anticipated economic results of the PFS will be realized or that commercial production at the past-producing Crean Hill mine will ever be achieved. A PFS is not a guarantee of economic viability and the results of the PFS may be materially affected by subsequent studies, changes in assumptions, project design, market conditions and other factors. Mineral resources that are not mineral reserves do not have demonstrated economic viability and, particularly, inferred mineral resources are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. Although the Company has attempted to identify important risks, uncertainties, contingencies and factors that could cause actual results to differ materially from those expressed or implied in forward-looking statements, there can be no certainty or assurance that the Company has accurately or adequately captured, accounted for or disclosed all such risks, uncertainties, contingencies or factors. Readers should place no reliance on forward-looking statements as actual results, performance or achievements may be materially different from those expressed or implied by such statements. Resource exploration and development, and mining operations, are highly speculative, characterized by several significant risks, which even a combination of careful evaluation, experience and knowledge will not eliminate. Forward-looking statements speak only as of the date they are made. The Company does not undertake to update any forward-looking statements, whether as a result of new information or future events or otherwise, except in accordance with applicable securities laws.

About Magna Mining Inc.

Magna Mining Inc. is a producing mining company with a strong portfolio of copper, nickel, and precious metals assets located in the world-class Sudbury mining district of Ontario, Canada. The Company’s McCreedy West Mine is currently in production, the adjacent Levack Mine is being restarted, and construction of the Crean Hill Project has been approved. These operations are supported by a pipeline of highly prospective past-producing properties including Podolsky, Kirkwood and Shakespeare.

Magna Mining is strategically positioned to unlock long-term shareholder value through continued production, exploration upside, and near-term development opportunities across its asset base.

Additional corporate and project information is available at www.magnamining.com and through the Company’s public filings on the SEDAR+ website at www.sedarplus.ca.

For further information, please contact:

Jason Jessup
Chief Executive Officer

or

Paul Fowler, CFA
Executive Vice President
705-482-9667
Email: info@magnamining.com

Photos accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/b9171140-a48f-49d2-bd96-021c9e03e979 

https://www.globenewswire.com/NewsRoom/AttachmentNg/2492931b-244d-4fd7-ac6d-3ee5409c6391


https://www.globenewswire.com/NewsRoom/AttachmentNg/c26f02ce-c440-497c-a30e-736e86b702cf

https://www.globenewswire.com/NewsRoom/AttachmentNg/7b666503-e01e-4a1c-a145-1fe2ba21a558 

https://www.globenewswire.com/NewsRoom/AttachmentNg/708632c8-6110-4e75-9315-5a3775073f58 

https://www.globenewswire.com/NewsRoom/AttachmentNg/ac9ec28e-a3bc-4a1a-85a4-6c2f807242ee 


Primary Logo

Figure 1

Location of Crean Hill and Key Sudbury Infrastructure
Figure 2

Crean Hill PFS Production Schedule & Contained Copper Equivalent Grade
Figure 3

Crean Hill PFS Copper Equivalent Payable Metal Production
Figure 4

Crean Hill PFS Pre-Tax Cash Flow
Figure 5

Sensitivity Analysis
Figure 6

Crean Hill Infrastructure and Geological Zones