Powerbank arranges 1:20 share rollback

2026-11-25 10:30 ET - News Release

Dr. Richard Lu reports

POWERBANK SHARES 2026 HIGHLIGHTS AND FISCAL 2027 UPDATES

Powerbank Corp. has shared highlights of its progress since its February, 2026, update, including a stronger balance sheet, a growing base of owned and operated assets, and new projects across the United States and Canada. Unless otherwise noted, all amounts are in Canadian dollars. Amounts for United States projects are in U.S. dollars.

  • $25.4-million refinancing reduces project debt by 14 per cent and is expected to release approximately $5.0-million in net cash;
  • IPP production delivered approximately 90 per cent of first quarter revenue at a 47-per-cent gross margin;
  • 23 U.S. solar and energy storage projects safe-harbored for Federal Investment Tax Credits.

Stronger balance sheet and growing independent power producer revenue

Powerbank's strategy of owning and operating the projects it builds is now showing up in its results. In the fiscal first quarter of 2027 (the three months ended Sept. 30, 2026), IPP production revenue was $3.76-million, approximately 90 per cent of total revenue, at a gross margin of 47 per cent. Working capital improved to $5.75-million as of Sept. 30, 2026, compared with $800,000 at June 30, 2026. Cash increased to $12.57-million and shareholders' equity increased to $26.01-million over the same period.

For the fiscal year ended June 30, 2026, IPP production revenue grew to $9.8-million from $9.3-million in fiscal 2025, gross margin improved to 34.7 per cent from 25.3 per cent, and net loss narrowed to $24.3-million from $31.1-million. Five projects reached commercial operation during the fiscal year.

On Oct. 26, 2026, the company completed a $25.4-million project-level refinancing across 53 operating solar projects. The refinancing consolidates 50 credit agreements into a single facility with a Canadian bank and reduces outstanding project loan principal by approximately $4.2-million, or 14 per cent. It is expected to release approximately $5.0-million in net cash to Powerbank, subject to the completion of all postclosing adjustments. The company will also bring operations and maintenance of 49 of these projects in-house.

Energy infrastructure for AI compute

On June 1, 2026, Powerbank added AI compute infrastructure and modular data centres as a strategic growth vertical alongside solar and battery storage, building on its experience in site acquisition, permitting, interconnection and long-term asset ownership. On June 29, 2026, the company signed a joint development agreement with Nodiac Corp. to deploy distributed AI compute infrastructure at Powerbank's North American solar and BESS sites, following a letter of intent signed on April 8, 2026.

On Oct. 29, 2026, the company announced its first two-megawatt modular data centre in Ontario, being developed with a joint development partner. The facility is designed to offer approximately 1.77 megawatts of leasable IT capacity. The estimated facility capital cost of approximately $10-million is to be financed by Powerbank and its partner, and commercial operation is targeted for fiscal 2028. No tenant agreement has been signed, and the project remains subject to zoning, building permit and financing.

U.S. projects safe-harbored for federal tax credits

On June 9, 2026, the company completed equipment procurement and physical work for eight distributed solar and energy storage projects, ahead of the July 4, 2026, deadline under the One Big Beautiful Bill Act. The projects carry an estimated $29.7-million (U.S.) in expected federal investment tax credits (ITCs), based on current project cost estimates and applicable ITC rates, and subject to satisfaction of all applicable eligibility requirements, which amounts may differ materially from actual credits realized. Together with the 15 New York projects procured in December, 2025, Powerbank has now safe-harbored 23 solar and energy storage projects which, subject to satisfaction of all applicable requirements, are expected to remain eligible for the ITCs.

On Aug. 18, 2026, the company reacquired the Gainesville and Highway 28 community solar projects in New York state for a combined purchase price of approximately $2.4-million (U.S.), payable in milestone installments rather than as an upfront lump sum. The projects total 13.9 MW, began physical work before the July 4, 2026, deadline, and carry approximately $13-million (U.S.) in expected ITCs. They add approximately $32.5-million (U.S.) of construction work to be delivered by Powerbank's subsidiary, Abundant Solar Power Inc., as EPC contractor.

The company added further owned projects in New York during the period. On July 20, 2026, it executed a lease for the Scofield project, a 3.2 MW DC community solar project in Broome county with approximately $3.2-million (U.S.) in expected ITCs and an estimated construction value of approximately $8-million (U.S.). On Sept. 3, 2026, it was awarded a contract through a competitive solicitation administered by the New York Power Authority to develop, build, own and operate a 1.628 MW DC solar project at SUNY Oneonta, which is expected to qualify for approximately $1.4-million (U.S.) in ITCs.

Powerbank also expanded its New York energy storage pipeline. On April 13, 2026, it executed a lease for the Conklin Hill Rd. project, a five MW AC solar and battery storage project eligible for incentives under NYSERDA's NY-Sun and Retail Storage Incentive programs. On May 21, 2026, it announced lease agreements for three battery energy storage projects in upstate New York, each designed for up to five MW AC with four-hour duration, for a combined 60 MWh (megawatt-hours). NYSERDA also approved approximately $3.4-million (U.S.) in incentives for the Elmira, Jordan Rd. 1 and Jordan Rd. 2 projects.

Construction and commercial operation

On March 17, 2026, the company began spring mobilization on nine New York state projects, including Jordan Rd. 1 and 2, Elmira, Newark and Camp Smith.

The 4.99 MW SFF 06 battery energy storage system (BESS) project in Ontario achieved commercial operation on April 20, 2026. All three projects in the 21 MW DC community solar portfolio in upstate New York reached commercial operation, and on June 30, 2026, the company executed an operations and maintenance services agreement covering the three projects.

On July 8, 2026, the company received a certificate of final completion for a 1.45 MW DC rooftop solar project in Calgary, Alta., built under an EPC agreement with Fiera Real Estate.

The 3.26 MW Camillus community solar project, built on a closed landfill in New York for Solar Advocate Development LLC under a $7.3-million (U.S.) transaction, achieved commercial operation on Oct. 13, 2026, and received permission to operate, as announced on Nov. 3, 2026.

On June 26, 2026, Abundant was awarded a $2.95-million (U.S.) federal contract with the U.S. Department of Defense and the Department of the Army for a covered parking canopy solar project, including electric vehicle chargers, at the Armed Forces Reserve Center in Farmingdale, N.Y.

Canadian growth in Ontario and Nova Scotia

On March 3, 2026, the company entered into an agreement with GrandBridge Corp. to jointly develop and invest in solar and storage projects of two MW AC or more within GrandBridge Energy's service territory in Ontario.

The company's 903 BESS project, which holds a 22-year IESO capacity contract and is owned equally by Powerbank and a partnership of first nations communities, received official plan amendment and zoning bylaw amendment approvals on July 21, 2026, completing its most complex permitting phase. On Sept. 15, 2026, the IESO approved the project's force majeure claim, extending its milestone commercial operation date to July 29, 2027.

The company also executed a lease for the four MW ON-765 West solar project in North Bruce Peninsula, Ont., and entered into a fee-for-service agreement to provide early development services for a BESS project to be submitted into the IESO LT2(c-2) capacity procurement. If a contract is awarded, Powerbank would hold a right of first refusal to act as EPC provider.

In Nova Scotia, all three of the community solar projects the company is developing, representing a 12.4 MW pipeline, secured interconnection agreements, and two of the three reached notice to proceed in August, 2026. The 6.86 MW Brooklyn project received its final environmental permit, with construction expected to begin in fall 2026. Brooklyn is owned and funded by AI Renewable Flow-through Fund, with Powerbank acting as lead developer under a fee-for-service arrangement, and is supported by up to $2,639,000 in federal clean technology investment tax credits and $1.92-million in grants. The company is also supporting TriMac Engineering, under a fee-for-service agreement, in providing solar feasibility and related assessments to the municipality of the county of Victoria, N.S.

Leadership and corporate updates

On Feb. 18, 2026, Andrew van Doorn was appointed president and chief operating officer. In August of 2026, Nicole Rusaw, CPA, CA, was appointed chief financial officer, succeeding Sam Sun. Ms. Rusaw brings more than 20 years of public company finance leadership.

Dr. Richard Lu, chief executive officer of Powerbank, commented: "Two thousand twenty-six is the year our transformation became visible in the numbers. Nine of every 10 dollars of revenue last quarter came from assets we own and operate, at a 47-per-cent gross margin, and our refinancing is expected to put approximately $5.0-million of cash back on our balance sheet. The world needs more power, for homes, for industry and now for AI, and we believe the companies that control generation, storage and sites will be at the centre of that buildout. With 23 U.S. projects safe-harbored for federal tax credits, a growing Canadian portfolio and our first modular data centre in development, we believe Powerbank is well positioned to be one of them."

Andrew van Doorn, president and chief operarting officer of Powerbank, added: "Our crews mobilized on nine New York projects this spring, and we brought new projects into commercial operation in Ontario and New York while meeting the July 4 safe harbor deadline. That is the result of a disciplined team and strong supplier relationships. We are now focused on converting our safe-harbored portfolio into construction and long-term owned assets."

The company notes that the execution of the company's growth strategy depends upon the continued availability of third party financing arrangements for the company and its customers and the company's future success depends partly on its ability to expand the pipeline of its energy business in several key markets. In addition, governments may revise, reduce or eliminate incentives and policy support schemes for solar and battery storage power, which could cause demand for the company's services to decline. The company's data centre and AI compute strategy is at an early stage, and the modular data centre project described above remains subject to securing tenants, zoning, permitting and financing. Further the forecasted MW capacity of a solar project may not be reached.

Share consolidation

The company also announces that the board of directors of the company, pursuant to authorization granted by shareholders at the company's annual general meeting, has approved the consolidation of its issued and outstanding common shares on the basis of one postconsolidated common share for every 20 preconsolidated common shares. The consolidation is being implemented to ensure that the company complies with the listing requirements of the Nasdaq.

The board has set Nov. 30, 2026, as the effective date of the consolidation and expects the common shares to trade on a postconsolidated basis at market open on Nov. 30, 2026, subject to final confirmation from the Cboe Canada Inc. and the Nasdaq. Upon completion of the consolidation, the Cusip and ISIN of the common shares will be changed to 73933V209 and CA73933V2093, respectively. The company's stock symbol on both the Cboe Canada and the Nasdaq shall be changed to POWB. The company's name will remain unchanged upon completion of the consolidation.

After giving effect to the consolidation, the common shares will be reduced from 61,878,420 to 3,093,921 common shares (without considering fractional rounding). No fractional common shares will be issued pursuant to the consolidation and any fractional shares that would otherwise be issued will be rounded up to the nearest whole number. The exercise price or conversion price and number of common shares issuable under any of the company's outstanding convertible securities will be proportionately adjusted in connection with the consolidation.

Shareholders of record as of the effective date will receive a letter of transmittal from Endeavor Trust Corp., the company's registrar and transfer agent for the common shares, providing instructions for the exchange of their common shares as soon as practicable following the effective date. Shareholders may also obtain a copy of the letter of transmittal by accessing the company's SEDAR+ profile or the company's EDGAR profile at the SEC website. Until surrendered, each share certificate or direct registration system statement representing preconsolidation common shares will be deemed for all purposes to represent the number of whole common shares to which the holder thereof is entitled as a result of the consolidation. Beneficial holders who hold their common shares through intermediaries (for example, a broker, bank, trust company investment dealer or other financial institution) and who have questions regarding how the consolidation will be processed should contact their intermediaries with respect to the consolidation.

About Powerbank Corp.

Powerbank is an independent renewable and clean energy project developer and owner focusing on distributed and community solar projects in Canada and the United States. The company develops solar and battery energy storage system (BESS) projects that sell electricity to utilities, commercial, industrial, municipal and residential off-takers. The company maximizes returns via a diverse portfolio of projects across multiple leading North America markets including projects with utilities, host off-takers, community solar and virtual net metering projects. The company has a potential development pipeline of almost one gigawatt and has developed renewable and clean energy projects with a combined capacity of over 100 megawatts built.