Trilogy Metals sets Arctic project permitting timeline

2026-07-16 11:24 ET - News Release

Mr. Tony Giardini reports

TRILOGY METALS ANNOUNCES PUBLICATION OF FEDERAL AND STATE PERMITTING SCHEDULE FOR ARCTIC PROJECT, ESTABLISHING DEFINED TIMELINE TOWARD A RECORD OF DECISION BY SEPTEMBER 2028

A co-ordinated federal and state permitting schedule for Trilogy Metals Inc.'s flagship Arctic project in northwestern Alaska's Ambler mining district has been published on the Federal Permitting Improvement Steering Council's permitting dashboard on-line. The high-grade Arctic copper-zinc-lead-gold-silver project is being advanced by Ambler Metals LLC, Trilogy's 50/50 joint venture with South32 Ltd.

Highlights

  • Federal permitting dashboard now displays an integrated schedule for Arctic project environmental review, with a targeted record of decision in September, 2028.
  • U.S. Army Corps of Engineers confirmed as lead federal agency for Arctic project environmental review.
  • Schedule integrates state of Alaska permitting under the first statewide FAST-41 memorandum of understanding in the nation -- the model since adopted by Idaho, Tennessee and Utah.
  • Milestone follows May, 2026, FAST-41 Covered project designation and April, 2026, Clean Water Act Section 404 permit application.
  • Targeted approximately 29-month timeline from Section 404 filing to record of decision -- inside the approximately 2.7-year permitting horizon contemplated by the permitting council -- state of Alaska memorandum of understanding.

The permitting schedule was published within the statutory 60-day window following the Arctic project's May 14, 2026, designation as a Covered project under FAST-41 (established by Title 41 of the Fixing America's Surface Transportation Act), and sets out a co-ordinated, publicly tracked timetable of federal environmental review and authorization milestones under the National Environmental Policy Act (NEPA). The U.S. Army Corps of Engineers (USACE), which is reviewing Ambler Metals' Clean Water Act Section 404 permit application filed on April 20, 2026, is confirmed as the project's lead federal agency.

State of Alaska permitting milestones for the Arctic project have been integrated into this single published schedule pursuant to the memorandum of understanding (MOU) signed in August, 2025, between the permitting council and the state of Alaska. Under that agreement -- the first statewide MOU of its kind between the permitting council and any state -- the State of Alaska agreed to opt into the FAST-41 process and to work with the permitting council and, where applicable, lead federal agencies such as the USACE, to align state permitting actions with the federal review timetable on the federal permitting dashboard. As a result, the Arctic project's schedule reflects both the federal environmental review process led by the USACE and the corresponding state permitting actions being coordinated by the Alaska Department of Natural Resources' Office of Project Management and Permitting, providing a single, synchronized road map for all major federal and state authorizations required to advance the project.

Alaska was the first state in the nation to enter into a statewide MOU with the permitting council, and that agreement has since served as the template for subsequent state partnerships, including those signed with Idaho, Tennessee and Utah. At the time of signing, the permitting council and the state projected that the framework could reduce the environmental permitting timeline for Alaska projects to approximately 2.7 years, from a historical baseline of approximately 3.6 years -- an efficiency gain of roughly 25 per cent. The Arctic project is among the first mining projects to be permitted under this federal-state framework, and its published schedule reflects that intended efficiency.

Under the published schedule, the USACE and cooperating agencies have committed to an estimated 29-month integrated review timetable, with key federal milestones including a notice of intent to prepare an environmental impact statement expected in September, 2026, publication of a draft environmental impact statement targeted for October, 2027, and a targeted record of decision in September, 2028, to be completed concurrently with State of Alaska and Northwest Arctic Borough permitting milestones.

The record of decision represents the culmination of the federal environmental review under NEPA; the remaining federal and state authorizations that follow the record of decision drive the schedule's targeted overall completion in November, 2028. Measured from the Section 404 permit application filed on April 20, 2026, the schedule targets a record of decision in approximately 29 months -- inside the approximately 2.7-year timeline contemplated when the permitting council and the State of Alaska signed their MOU, and materially ahead of the historical baseline for comparable federal reviews. All dates and milestones are publicly viewable and subject to continuing tracking on the federal permitting dashboard.

Tony Giardini, president and chief executive officer of Trilogy, commented: "The publication of this schedule is a significant milestone under the Arctic project's FAST-41 status, giving our shareholders, the state of Alaska and local stakeholders a transparent, publicly tracked road map for federal and state review. With the USACE confirmed as the lead federal agency and Alaska's permitting integrated into the same timetable, this is exactly the kind of co-ordinated, predictable process FAST-41 was designed to deliver. Alaska was the first state in the country to sign a statewide agreement with the permitting council, and the Arctic project is now among the first mining projects to be permitted under that framework -- on a timeline that is not only transparent, but demonstrably more efficient than the historical norm. We look forward to continued close engagement with our federal and state agency partners and local communities as the review advances. For our shareholders, a published timetable turns permitting from an open-ended risk into a defined, publicly tracked sequence of milestones -- and it brings a record of decision, and with it a construction decision on one of the world's highest-grade undeveloped copper deposits, clearly into view."

Ron Rimelman, president of Ambler Metals, commented: "We will continue to work hand in hand with our federal and state partners to meet each milestone, while continuing to build trust and keep regional stakeholders informed at every stage. Alaska has an unrivalled track record of responsible resource development that balances industry with the protection of our wildlife and landscapes, and we will uphold that standard throughout this schedule and beyond."

For more information about the FAST-41 permitting program, see Trilogy's news release dated May 15, 2026.

Arctic project FAST-41 timeline to date

  • August, 2025: The permitting council and the State of Alaska signed a statewide MOU to integrate federal and state permitting schedules for eligible Alaska infrastructure projects. It was the first statewide agreement of its kind between the permitting council and any state, and has since been used as the template for MOUs with Idaho, Tennessee and Utah.
  • April 20, 2026: Ambler Metals filed an application for a Clean Water Act Section 404 permit with the USACE, initiating federal permitting for the Arctic project.
  • May 14, 2026: The Arctic project was posted as a FAST-41 Covered project on the federal permitting dashboard, with the USACE confirmed as the lead federal agency.
  • July 13, 2026: The co-ordinated federal and state permitting schedule was published on the federal permitting dashboard, establishing the timetable of milestones for the Arctic project's federal and state review.

About Trilogy Metals Inc.

Trilogy Metals is a metal exploration and development company holding a 50-per-cent interest in Ambler Metals LLC, which has a 100-per-cent interest in the Upper Kobuk mineral projects (UKMP) in northwestern Alaska. On Dec. 19, 2019, South32, a globally diversified mining and metals company, exercised its option to form a 50/50 joint venture with Trilogy Metals. The UKMP is located within the Ambler mining district, which is one of the richest and most prospective known copper-dominant districts in the world. It hosts polymetallic volcanogenic massive sulphide (VMS) deposits that contain copper, zinc, lead, gold and silver, and carbonate replacement deposits which have been found to host high-grade copper and cobalt mineralization. Exploration efforts have been focused on two deposits in the Ambler mining district -- the Arctic VMS deposit and the Bornite carbonate replacement deposit. Both deposits are located within a land package that spans approximately 190,929 hectares. Ambler Metals has an agreement with NANA Regional Corp. Inc., an Alaska native corporation, that provides a framework for the exploration and potential development of the Ambler mining district in co-operation with local communities. Trilogy Metals' vision is to develop the Ambler mining district into a premier North American copper producer while protecting and respecting subsistence livelihoods.