VIZSLA SILVER PROVIDES UPDATE ON PANUCO PROJECT DEVELOPMENT
Vizsla Silver Corp. has provided an update on the continued advancement of its wholly owned Panuco silver-gold project in Mexico.
Vizsla Silver continues to advance key development activities at Panuco with a focus on construction readiness. M3 Engineering & Technology has now completed approximately 50 per cent of engineering and approximately 85 per cent of the process plant equipment currently contemplated for the project has been ordered. As previously disclosed, three key development contracts for the project have been awarded, including engineering procurement and construction management (EPCM), mine design and equipment supply (see press releases dated April 23, 2026, and June 16, 2026, respectively), with the main mining contract to be awarded in due course. In parallel, the company continues to work closely with Mexican federal authorities to strengthen security arrangements in preparation for a phased return to site.
"We have made significant progress advancing Panuco this year, achieving important milestones in engineering, procurement and development planning," said Michael Konnert, president and chief executive officer. "We are well positioned to
move into the next phase of development, with safety guiding our preparations for a phased return to site and first silver production now anticipated in the second half of 2028."
"This progress has come during an exceptionally difficult year,
and we have remained focused on supporting our people, their families and the communities in which we operate. We stand by the families of our colleagues and share their grief in this profound loss as well as their need for answers. We continue to support the Mexican authorities in their ongoing investigation. Our commitment to the families of our colleagues is enduring, as is our belief in Panuco's future and its potential to create lasting opportunities for the communities in Sinaloa and the people of Mexico."
Long-term support and the Vizsla Foundation
Since February, 2026, Vizsla Silver has been working toward establishing the Vizsla Foundation as part of its long-term commitment to the people and communities of Sinaloa. The foundation is intended to complement the direct assistance the company continues to provide to the families impacted by the tragic events of January, 2026, by focusing on providing meaningful, publicly available, multigenerational support and lasting opportunities to individuals and families across local communities.
The company continues to engage with the local communities to help shape the foundation's priorities and long-term initiatives, including support for education, health and economic development in the communities surrounding Panuco. Further details regarding the foundation's structure and programs will be shared as plans progress and discussions with families continue.
Vizsla Silver has committed to making an initial contribution of $5-million (U.S.) to the foundation, with plans to also direct a percentage of future profits toward sustaining its work.
Security and site readiness
The safety of employees and contractors remains central and continues to guide the company's planning for a return to site. Vizsla Silver continues to work closely with Mexican federal authorities and third party security advisers to support additional security infrastructure, enhance overall security measures and strengthen on-site support in preparation for a phased return. These efforts build on the company's established approach to security, which has included a significant investment in security resources, third party risk assessments, and adjustments to or suspension of activities in response to changing conditions. The timing and scope of any formal return to the project site will be informed by the company's assessment of security conditions and readiness.
Updated project guidance
The company has revised its targeted first silver production at Panuco to the second half of 2028 from the second half of 2027 previously. The revised development schedule reflects the company's current expectations for permitting, site readiness and construction timing.
Except for the updated development timeline, the company is not updating the operating, capital or economic parameters disclosed in the company's November, 2025, feasibility study. The company has not made a production decision for Panuco (see "No production decision" below). A summary of key parameters from the feasibility study, other than the revised first-production target, is set out below.
Qualified person
The scientific and technical information contained in this news release has been reviewed and approved by Dave D'Antonio, PEng, senior vice-president of technical services for Vizsla Silver, a qualified person as defined in National Instrument 43-101, Standards of Disclosure for Mineral Projects.
About Vizsla Silver
Corp.
Vizsla Silver is a Canadian development company advancing Panuco, its 100-per-cent-owned silver-gold project in Sinaloa, Mexico. The November, 2025, feasibility study outlines annual production of 17.4 million ounces silver equivalent over an initial 9.4-year mine life, an after-tax net present value (discounted at 5 per cent) of $1.8-billion (U.S.), a 111-per-cent internal rate of return and a seven-month payback at $35.50 (U.S.) per ounce silver and $3,100 (U.S.) per ounce gold. Vizsla Silver is concurrently advancing mine development and district-scale exploration with the objective of becoming a leading primary silver producer.
No production decision
The company has not made a production decision for the project. A decision to proceed with construction will only be made following the completion and review of detailed engineering, financing arrangements, and receipt of all required permits and approvals.