Mr. Brian Park reports
TRILLION ENERGY ANNOUNCES COMMENCEMENT OF OPERATIONS ON TRIPODS
Trillion Energy International Inc. has continued the velocity string tubing program on two tripods after previously completing operations on the Akcakoca platform in late November.
This week, a crane barge arrived at the SASB gas field to transport the snubbing unit from the Akcakoca platform to the Akkaya tripod for the next operation on the Alapli-2 well where 2,996 metres of 2-3/8th tubing will be run.
Following the completion of Alapli-2, the crane barge will move the snubbing unit to the East Ayazli tripod where 2,888 metres of 2-3/8th VS tubing will be run in the Bayhanli-2 well.
Trillion will use three sets of burst discs in each well to float the tubing in the horizontal section of the wells during installation, which will then be ruptured. The crane barge and snubbing crew will be released once the VS string is run in the wells safely, following which, nitrogen stimulation activities will occur. Nitrogen lifting has been recently proven effective in kicking off the gas wells to date.
The whole operation is expected to be completed within approximately two weeks, weather permitting.
The company and its technical advisers will continue working on site to optimize production. Gas lift compressors are currently being sized for various wells, the first being South Akcakoca.
About
Trillion Energy International Inc.
Trillion Energy International is focused on oil and natural gas production for Europe and Turkey with natural gas assets in Turkey. The company is 49-per-cent owner of the SASB natural gas field, a Black Sea natural gas development and a 19.6-per-cent (except three wells with 9.8-per-cent) interest in the Cendere oil field.
We seek Safe Harbor.
© 2025 Canjex Publishing Ltd. All rights reserved.